Issue details

Wakefield Eastern Relief Road compensation claims under Part 1 of the Land Compensation Act 1973

To consider an injection of funding into the capital programme for costs associated with claims under the Land Compensation Act 1973 following the opening of the Wakefield Eastern Relief Road.

 

ID No: 1946/0124

Decision type: Key

Decision status: Recommendations Approved

Notice of proposed decision first published: 01/12/2023

Overview and Scrutiny: Climate Change and Environmental Wellbeing - Chair, Cllr A Wallis;

Decision due: March 2024 by Cabinet

Contact: Martin Barnes, Service Manager, Highways, Infrastructure and Traffic Management Email: mbarnes@wakefield.gov.uk Tel: 0345 8 506 506.

Date First Included in Plan: January 2024

Reason for Removal: Approved at Cabinet on 19 March 2024.

Decisions